NSW - Sydney Hutchison Ports Planned Terminal Outage (High Voltage Power & TOS Upgrade) February 20-22 2026

09 Feb 2026
  • Copy to clipboardLink Copied

Please be advised that Hutchison Ports Sydney has confirmed a major planned terminal outage to facilitate critical High Voltage Power and Terminal Operating System (TOS) upgrades.

Planned Outage Details

  • Start: Friday, 20 February 2026 – 06:00
  • End: Sunday, 22 February 2026 – 06:00
  • Duration: 48 hours

During this period, the terminal will not be operating in any capacity.

Operational Impact

  • No vessel, road, or rail operations will take place
  • No container receivals, deliveries, or documentation processing will be available
  • Delays should be expected before and after the outage as operations resume and backlogs are cleared

Customers are requested to adjust schedules accordingly and factor this outage into planning for import and export cargo via Hutchison Sydney.

KLN will continue to monitor and manage impacts where possible and will advise if further information becomes available.

If you have any questions or require assistance with shipment planning around this outage, please contact your KLN Customer Service Team.